Hotel PIP cost and timeline estimator.

Estimate a property improvement plan: the total budget, cost per key, the room revenue the work displaces, and the monthly spend it takes to finish by the brand's deadline. Runs in your browser; nothing is saved.

Hotel PIP Cost Estimator

Every starting figure, including the cost per key for each scope tier, is an example. Example — change to yours. They are not industry data; use your PIP scope, bids and brand standards.

Guest room scope: cost per key

Adds furniture, lighting, artwork. Example figure: enter your own per-key cost or bid.

Lobby, F&B, meeting space, exterior

Rooms out of service

You'd have sold

Your PIP

Total PIP budget
$3,465,000
$2,400,000 guest rooms + $750,000 public areas + $315,000 contingency
Per key
$28,875
Total budget ÷ 120 keys, public areas and contingency included
Room revenue displaced
$126,000
1,200 room nights out of service · $3,591,000 with the budget

An estimate from the numbers you entered, not a quote or a bid. Excludes financing, design fees and taxes unless you include them in the inputs. Real spend is rarely even: deposits and long-lead FF&E come early.

Track the PIP deadline, budget and change orders in one place

Calculator by Ardn Cloud Solutions

How to use this calculator

  1. Enter the hotel's rooms (keys).
  2. Pick the guest room scope and enter your cost per key. The three tiers start with example figures; overwrite them with your PIP scope or contractor bids.
  3. Add the public areas budget and the contingency you want to carry.
  4. Enter how many nights each room will be out of service, the occupancy you would have run on those nights, and your ADR.
  5. Set the PIP completion deadline to see the months left and the average monthly spend needed to meet it.

How the numbers are worked out

Construction = rooms × cost per key + public areas budget
Total PIP budget = construction × (1 + contingency %)
Per key = total PIP budget ÷ rooms
Revenue displaced = rooms × nights out per room × occupancy % × ADR
Months left = days from today to the deadline ÷ 30.44
Monthly spend pace = total PIP budget ÷ months left

Per key includes public areas and contingency, so it is the all-in budget per room, higher than the guest room cost per key you entered. Revenue displaced counts room revenue only; add lost food and beverage or meeting revenue separately if public areas close.

Questions

What is a hotel PIP?

A property improvement plan (PIP) is the list of upgrades a hotel brand requires, usually at a sale, a refinancing, a franchise renewal or a conversion to the brand, with a date by which the work must be finished. It can cover guest rooms, public areas, exterior and systems.

How do you estimate a PIP budget?

Multiply the number of keys by the cost per key for the guest room scope, add the budget for public areas and anything else outside the rooms, then add a contingency percentage on top. 120 keys at $20,000 is $2,400,000; add $750,000 of public areas and a 10% contingency and the PIP budget is $3,465,000, or $28,875 per key.

Where do the cost-per-key figures come from?

They are example inputs so the calculator works on first load, not industry data or a benchmark. Per-key cost depends on the brand's scope, the hotel's condition, the market and what is already compliant. Replace them with the figures from your PIP, your contractor's bids or your own past projects.

How do you estimate revenue displaced by a renovation?

Multiply the rooms by the nights each room is out of service to get room nights out, then by the share of those nights you would have sold and your ADR. 120 rooms out for 10 nights each is 1,200 room nights; at 70% occupancy and a $150 ADR that is $126,000 of room revenue displaced.

What is monthly spend pace?

The total PIP budget divided by the months left until the deadline: the average you would need to spend each month to finish on time. Real spend is uneven, with deposits and long-lead furniture early and punch-list work late, so use it to test whether the deadline is realistic, not as a draw schedule.

Running the PIP in a spreadsheet? Rimas360 hotel PIP management software puts every PIP deadline on a capital clock beside franchise terms and loan maturities, then runs the work with budgets, change orders, room phasing, bid packages and a lender report.